Question: 9 points How Did I Do ? table [ [ Activity , Normal Time ( weeks ) , Crashed Time ( weeks ) ,

9 points
How Did I Do?
\table[[Activity,Normal Time (weeks),Crashed Time (weeks),Normal Cost,Crashed Cost,Predecessor(s)],[A,5,3,$900,$1,700,],[B,6,5,$350,$400,-],[C,6,5,$450,$675,-],[D,3,2,$900,$1,050,A],[E,5,3,$1,350,$2,550,C],[F,6,3,$825,$1,425,B]]
What is the duration of the project (in weeks)?
What is the target duration of the project (after crashing the project)?
By how many weeks should activity A be crashed?
Number
By how many weeks should activity B be crashed?
Number
By how many weeks should activity C be crashed?
By how many weeks should activity D be crashed?
Number
By how many weeks should activity E be crashed?
By how many weeks should activity F be crashed?
What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)?(Display your answer to two decimal places.)
 9 points How Did I Do? \table[[Activity,Normal Time (weeks),Crashed Time (weeks),Normal

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!