Question: 9. The document used to provide authorization for beginning planning and establishes the boundaries of the project is called the a. Stakeholder Engagement Strategy b.
9. The document used to provide authorization for beginning planning and establishes the boundaries of the project is called the a. Stakeholder Engagement Strategy b. Project charter c. Operating agreement d. Business Case 10. What are the three characteristics of potential project stakeholders? a. b. c. 11. The system must have an operational availability of 95% is an example of which type of requirement? a. Functional b. Non-functional c. Binary Id. Traceable 12. The agreed upon set of requirements is called which of the following? a. List of Exclusions b. List of Inclusions c. Desired d. Functional 13. What are the two types of scope for any project? a. Product, design b. Project, program c. Product, Project d. Portfolio, Program