Question: 9. The following data is given for the Stringer Company: Budgeted production 933 units Actual production 1,034 units Materials: Standard price per ounce $1.75 Standard
9. The following data is given for the Stringer Company:
| Budgeted production | 933 units |
| Actual production | 1,034 units |
| Materials: | |
| Standard price per ounce | $1.75 |
| Standard ounces per completed unit | 12 |
| Actual ounces purchased and used in production | 12,780 |
| Actual price paid for materials | $26,199 |
| Labor: | |
| Standard hourly labor rate | $14.44 per hour |
| Standard hours allowed per completed unit | 4.6 |
| Actual labor hours worked | 5,325.1 |
| Actual total labor costs | $81,208 |
| Overhead: | |
| Actual and budgeted fixed overhead | $1,057,000 |
| Standard variable overhead rate | $24.00 per standard labor hour |
| Actual variable overhead costs | $149,103 |
| Overhead is applied on standard labor hours. | |
The direct materials quantity variance is
a.3,834.00 favorable
b.3,834.00 unfavorable
c.651.00 unfavorable
d.651.00 favorable
11.
The Lucy Corporation purchased and used 129,000 board feet of lumber in production, at a total cost of $1,548,000. Original production had been budgeted for 22,000 units with a standard material quantity of 5.7 board feet per unit and a standard price of $12 per board foot. Actual production was 23,500 units. The materials price variance is
a.$6,000 unfavorable
b.$0
c.$59,400 unfavorable
d.$59,400 favorable
15.
The following data relate to direct labor costs for the current period:
| Standard costs | 7,300 hours at $11.40 |
| Actual costs | 6,300 hours at $10.50 |
What is the direct labor rate variance?
a.$17,070 unfavorable
b.$5,670 favorable
c.$17,070 favorable
d.$11,400 favorable
16.
The standard costs and actual costs for direct materials for the manufacture of 2,400 actual units of product are
| Standard Costs | |
| Direct materials (per completed unit) | 1,040 kilograms @$8.94 |
| Actual Costs | |
| Direct materials | 2,400 kilograms @ $8.10 |
Round your final answer to the nearest dollar.
The amount of direct materials price variance is
a.$2,016 favorable
b.$874 favorable
c.$2,016 unfavorable
d.$874 unfavorable
6.
-
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.99; actual, $2.05 Standard yards per unit: standard, 4.61 yards; actual, 4.98 yards Units of production: 9,200 Calculate the direct materials quantity variance.
a.$6,773.96 favorable
b.$6,978.20 favorable
c.$6,978.20 unfavorable
d.$6,773.96 unfavorable
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
