Question: 9 You are improving a metric called Cycle Time. This is the time taken for raw materials that go through the different internal processes and
You are improving a metric called Cycle Time. This is the time taken for raw materials that go through the different internal processes and convert into finished goods. You capture one data point each day. Which control chart will you use to monitor this metric.
Bar R Chart
IMR Chart
C Chart