Question: 9. You are preparing your monthly status report for your project. Assuming the variances to date are not unusual, what would the ETC be assuming
9. You are preparing your monthly status report for your project. Assuming the variances to date are not unusual, what would the ETC be assuming your project was budgeted to cost US $125,000 and take 12 months to complete and you have actually spent US $42,000, produced US $37,500 worth of the product and were scheduled to have spent US $39,000?