Question: 9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available

9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for each activity: Activity Activity Predecessor Time (Weeks) 1 3 2 - 7 3 1 2 456 N 2 5 2 6 4 1 7 5 4