Question: 9.7 - Payback Period Compute the payback period for a project that requires an initial outlay of $153,425 that is expected to generate $40,000 per

9.7 - Payback Period Compute the payback period for a project that requires an initial outlay of $153,425 that is expected to generate $40,000 per year for 9 years.