Question: 9.what is the correct answer? (it can be one more than correct answer) Table below gives the activities of a project, their predecessor(s), and their

9.what is the correct answer? (it can be one more

9.what is the correct answer? (it can be one more than correct answer)

Table below gives the activities of a project, their predecessor(s), and their durations. Select the option that make the statement correct. The path is a critical path of the project. Activity Predecessor Duration A 2 B 4 C A 8 A 4 E B 14 F D 8 G C, E, F 9