Question: ( a ) ( 1 2 points ) Now consider the task set { ( 1 0 , 2 ) , ( 1 2 ,

(a)(12 points) Now consider the task set {(10,2),(12,6),(25,9,20)}, This task set is not
schedulable with the RM algorithm. We want to reduce the execution time of the task
with period 12 to make the task system schedulable with the RM algorithm. How large
can the execution time of the task with period 12 be? Write a brief description of the
method you used to find this amount.
(b)(10 points) Consider the task set {(7,10,1,10),(12,6),(25,9)}. Its total utilization is 0.96.
Is the task set schedulable with the RM algorithm? Explain how you reached your
conclusion.
I don't understand in the a part do I need perform Time demand analysis, if so how, what would be the value of t I will be considering?
and the second part, do I need to perfororm TDA for b part as well? Is there an easier way to do it?
 (a)(12 points) Now consider the task set {(10,2),(12,6),(25,9,20)}, This task set

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!