Question: A) 1.29 B) 0.78 C) 1.0 D) 0.49 All tasks on your Project are using the 50% -50% rule. For the status date shown in
A) 1.29
B) 0.78
C) 1.0
D) 0.49
All tasks on your Project are using the 50% -50% rule. For the status date shown in the figure below, what is your SPI? Budget-6 J F M A 14 12 M J 10 Status Date 12 A 12 Work packages A 10 A J A S O N D
Step by Step Solution
3.30 Rating (156 Votes )
There are 3 Steps involved in it
The correct answer is A 129 The SPI Schedule Performance Index is calculated by dividing the Earned ... View full answer