Question: a - 2 . For each method, find the average job flow time and the average job tardiness. ( Round your ar table [

a-2. For each method, find the average job flow time and the average job tardiness. (Round your ar
\table[[,\table[[First Come,],[First Served]],\table[[Shortest],[Processing],[Time]],\table[[Earliest Due],[Date]],Critical Ratio],[Average flow time,12.50,11.33,11.58,12.08],[Average job tardiness,2.83,0.83,0.42,0.67]]