Question: A _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ is called when the contractor has completed the initial

A _______________ is called when the contractor has completed the initial conceptual specifications, drawings, or flowcharts and the customers agreement is sought.
preliminary design review meeting
project status review meeting
final design review meeting
problem-solving meeting