Question: A . $ 3 , 4 0 0 , 0 0 0 B . $ 3 , 8 0 0 , 0 0 0 C

A. $3,400,000
B. $3,800,000
C. $3,200,000
D. $4,000,000
21. For the problem in 20, what is the BCWS?
A. $3,400,000
B. $3,800,000
C. $3,200,000
D. $4,000,000
22. For the problem in 20, what is the ACWP?
A. $3,400,000
B. $3,800,000
C. $3,200,000
D. $4,000,000
23. For the problem in 20, what is the TV?
A.+20 days
B.-20 days
C.-10 days
D.+10 days
24. For the problem in 20, what is the FAC. Assume rate of progress prevailing to date will continue to prevail until project completion.
A. $3,368,421
B. $4,750,000
C. $4,000,000