Question: A 3-station flow line has deterministic processing times (6, 9, 10). 1. What are the raw processing time, bottleneck rate and critical WIP for the

A 3-station flow line has deterministic processing times (6, 9, 10).

1. What are the raw processing time, bottleneck rate and critical WIP for the line?

2. What is the maximum WIP allowed to maintain a minimized cycle time?