Question: A 4 MGD ( 2 0 , 0 0 0 m / day ) of industrial wastewater having BOD 5 concentration of 1 0 0

A4MGD (20,000m/day) of industrial wastewater having BOD5 concentration of 1000my L, and reaction rate of 4.0/day is generated by industries at a city's industrial park.Because of the high BOD5, there is a plan to build an industrial pre-treatment system at an industrial park. Effluent from the pre-treatment will be discharged into the city sewer for final polishing at the city wastewater treatment plant. Determine percent BD5 removal if the wastewater is treated in two continuous flow stirred tank reactors in parallel with equal flow to each reactor having a volume of 2500m*?