Question: a . ( 5 pts ) Write the product structure diagram of Product 1 as an intended bill - of - materials ( BOM )

a.(5 pts) Write the product structure diagram of Product 1 as an intended bill-of-materials
(BOM) list.
b.(10 pts) Calculate the net requirement schedule for assembly Z based on the given product
structure diagrams of product 1 and 2. Show your calculations.
c.(20 pts) Using the Least Unit Cost (LUC) technique, create the planned order release for
Assembly Z. Assume a set-up cost of 300 TL and a holding cost of 2 TL per unit per week.
Calculate the total cost. Show your calculations.
d.(5 pts) Is the corresponding solution optimal? Why/ why not? Explain.