Question: a ) ( 8 pts . ) Running this line as a push system, and with a single machine in each stage, what is the

a)(8 pts.) Running this line as a push system, and with a single machine in
each stage, what is the maximum number of units the line can produce in
an 18-hour (yes, they work from 6AM to 12AM) day? (Hint: maximize the
throughput while assuring the CT is 3-hours or shorter.)
b)(16 pts.) Mr. Aramazo has been approached by John OCush, an
entrepreneur and a long-time customer. Mr. OCush believes he can
increase the sales to 300 units per day easily. The first thought that crosses
Mr. Aramazos mind is that he needs to set up a number of parallel lines,
consisting of a single machine per stage but he quickly figures thats not
practical for many reasons. Instead, he decides to add parallel machines in
each stage but preserve the structure of a single line. Under the same 3-
hour cycle-time constraint, what are the minimum number of machines at
each stage to produce the desired 300 units in 18 hours? (Hint: If there are
multiple solutions with the same minimum total number of machines,
choose the one that also minimizes the cycle-time.)
c)(8 pts.) Whats the cycle time of the line with multiple machines per stage
designed in part b?
d)(8 pts.) Interpret the results obtained in parts b and c, in comparison to
running multiple independent lines (with a single machine in each stage) in
parallel. What factors contribute to the efficiencies you observe?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!