Question: a. A large stadium is planning to develop a new computer program to keep track of the members and trainers. An initial study has determined
a. A large stadium is planning to develop a new computer program to keep track of the members and trainers. An initial study has determined that the size of the program will be roughly 25,000 delivered source instructions. This project is a good example of an Organic software project. ab bb Cb dp 2.4 1.05 2.6 0.38 Software project Organic Semi-detached Embedded 3.0 1.12 2.6 0.35 3.6 1.20 2.6 0.32 Using the Basic COCOMO equations, calculate the following: 1. Effort applied in person month (2 Marks) II. Time required to complete the project (2 Marks) III. Average Staffing (1 Mark) Productivity (1 Mark) IV