Question: a) Activity that should be crashed first to reduce the project duration by 1 day is(___). B.) activity that should be crashed next to reduce

a) Activity that should be crashed first to a) Activity that should be crashed first to reduce the project duration by 1 day is(___).

B.) activity that should be crashed next to reduce the project duration by one additional day is (__).

C.) the total cost of crashing the project by 2 days =$.

Three activities are candidates for crashing on a project network for a large computer installation (al are, of course, critical). Activity details are in the following table Normal Time Crash Time Normal Activity (days) (days) Cost 7 6 $5,000 B 4 2 $1,200 11 9 $4,200 Total Cost with Crashing Immediate Predecessor(s) $5,500 $3,000 $6,400

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!