Question: a . After installing foundations for the identical towers A and B , a plinth has to be erected for tower B to compensate for

a. After installing foundations for the identical towers A and B, a plinth has to be
erected for tower B to compensate for the hill slope. On completion of the plinth a
sighting is taken from its top to determine the height of base to be constructed for
tower A to ensure final levelling. The foot of each tower is clamped in position by
a series of securing plates fitted to base A and the plinth.
b. The activities to be considered with their estimated duration and manpower
requirements are:
c. Produce an "activity on arrow" network for the project identifying the critical path
and determine the minimum duration of the project in days. Show total float and
free float on your network.
d. Produce a tabulated, job oriented, analysis of the network
e. Produce a bar chart representation of the network and a resource diagram for
the project.
f. What will be the effect if the digging of foundation A(activity B) was extended to
i.6 Days
ii.8 days
If the maximum number of men available on any day was six, could the project be
completed in the minimum time determined in part d assuming the digging of
foundation A took the two days scheduled.
a . After installing foundations for the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!