Question: A agrees to build a machine for B by September 1 for $ 3 0 0 0 . 0 0 . On August 1 5

A agrees to build a machine for B by September 1 for $3000.00. On August 15, both A and B agree not to proceed with the contract. In this situation,
a.
. the contract has been discharged by a condition precedent.
b.
the contract has not been discharged and the parties must complete their respective obligations
c.
the contract has been discharged by a condition subsequent.
d.
the contract has been discharged by anticipatory breach.
e.
the contract has been discharged by waiver.