Question: a. b. C. A B C D J K d E H F G Pred. Optimistic timeMost Likely timePessimistic time 15 9 19 11 14

a. b. C. A B C D J K d E H F G Pred. Optimistic timeMost Likely timePessimistic time 15 9 19 11 14 9 A A A B,C C D F,G E H,I J 10 4 8 7 8 4 6 9 5 3 10 12 7 11 9 11 6 8 11 8 5 15 Draw the Network Diagram? (5 Points) Find the Critical Variance? (2 Points) What is the Project Duration? ( 2 Points) What is the Proiect Critical Path? (2 Points) 10 14 9 7 20
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
