Question: A B C Activity Predecessor D E F G H conduct a consumer test panel study. Crash Schedule The following data were obtained from

A B C Activity Predecessor D E F G H conduct a consumer test panel study. Crash Schedule The following data were obtained from a study of the times required to A B C, D C, D E F Time (Weeks) 4 2 6 2 5 4 5 1 Cost Time (Thousands $) (Weeks) 6 5 4 10 4 7 6 9 6 2 5 6 11 6 5 4 Normal Schedule Cost (Thousands $) 4 3 4 4 6 3 2 2 Crash Rate 2 0.5 0.75 0.5 0.5 1.5 0 1 a) Find the all normal schedule and cost. b) Find the least-cost plan to complete the project in 21 days. (Assume minimum partial crashing of 1 week)
Step by Step Solution
3.51 Rating (151 Votes )
There are 3 Steps involved in it
ANSWER a To find the normal schedule and cost we do not need the crash schedule and crash rate We can simply use the normal schedule and the cost given in the table Activity Predecessor Normal Schedul... View full answer