Question: A: B: C: D: E: F: begin{tabular}{cccc} hline Activity & a & m & b hline A & 11 & 15 & 19

A: B: C: D: E: F: \begin{tabular}{cccc} \hline

A:

B:

C: D: E: F:

\begin{tabular}{cccc} \hline Activity & a & m & b \\ \hline A & 11 & 15 & 19 \\ B & 27 & 31 & 41 \\ C & 18 & 18 & 18 \\ D & 8 & 13 & 19 \\ E & 17 & 18 & 20 \\ F & 16 & 19 & 22 \\ \hline \end{tabular} Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places)