Question: A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 B D E 7 3 6 3

A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 B D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E End Start D Activity Normal time (days) Normal cost Crash time Crash cost 3 A B D E 7 3 6 $300 $250 $400 $200 S300 1 4 $800 $350 $900 $500 $550 3 2 2 1 a) Give the crash cost per day per activity (5 points) b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities? (3 points) c) Find the new budget (or cost of the project), (2 points) HI a e ew