Question: A bank has a drive through with 4 parallel tellers. Tellers take 8 minutes to process a customer. Each hour the tellers are down for
A bank has a drive through with 4 parallel tellers. Tellers take 8 minutes to process a customer. Each hour the tellers are down for 3 minutes to change the till. The capacity of the system per hour is:
Round the number up to the nearest higher integer.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts