Question: a ) Based on the given information regarding the activities for the project, the project completion date = 1 4 weeks. Part 3 b )
a Based on the given information regarding the activities for the project, the project completion date
weeks.
Part
b To reduce the duration of the project to weeks at the least cost the following is the order of what needs to be followed while crashing the activities:
Part
The first activity to crash is
D
by weeks at a per week crashing cost of
dollars.
Part
Next one should crash activity D and activity
E
by weeks for an additional total per week crashing cost of
dollars.
Part
c New requirements are to reduce the project to weeks. Continuing to crash the activities from weeks based on the above crashing already completed, the following is the order for crashing:
Part
Next activity to crash in order is
G
by weeks at a per week crashing cost of
dollars.
Part
Next one should crash activity
A
and activity E by week at a total per week crashing cost of
dollars.
Part
Total cost of crashing the project to weeks
eKimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table:nter your response here dollars.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock