Question: a ) Based on the given information regarding the activities for the project, the project completion date = weeks. b ) To reduce the duration

a) Based on the given information regarding the activities for the project, the project completion date = weeks.
b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities:
The first activity to crash is
by 2 weeks at a per week crashing cost of dollars.
Next, one should crash activity D and activity
by 2 weeks for an additional total per week crashing cost of
dollars.
c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, the following is the order for crashing:
Next activity to crash in order is
by 2 weeks at a per week crashing cost of dollars.
Next, one should crash activity
and activity E by 1 week at a total per week crashing cost of
dollars.
Total cost of crashing the project to 7 weeks : ] dollars.
 a) Based on the given information regarding the activities for the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!