Question: a ) based on the given information regarding the activities for the project, the project completion date = _ _ weeks b ) to reduce
a based on the given information regarding the activities for the project, the project completion date weeks
b to reduce the duration of the project to weeks at the lease cost, the following is the order of what needs to be followed while crashing the activities: the first activity to crash is by weeks for an additional total per week crashing cost of dollars
c new requirements are to reduce the project to seven weeks. Continue to crash the activities from weeks based on the above crashing already completed, the following is the order for crashing:
next activity to crash in order is by two weeks out of her crushing cost of dollars
Next, one should crash activity and activity E by one week at a total per week crashing cost of dollars.
Total cost of crashing the project to seven weeks dollars
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
