Question: a) Based on the given information regarding the activities for the project, the project length = _______ weeks. Part 3 b) The total cost required

a) Based on the given information regarding the activities for the project, the project length =
_______ weeks.
Part 3
b) The total cost required for completing this project on normal time =
$_______.
Part 4
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
_______
.
Part 5
The cost of the project based on the first activity selected for crashing will increase by
_______
Part 6
d) The maximum weeks by which the project can be reduced by crashing =
_______
weeks.
Part 7
Total cost of crashing the project to minimum (or maximum weeks possible) =
_______
Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts