Question: a). based on the given information regarding the activities for the project, the project lenght = ___ weeks. b). the total cost required for completing

a). based on the given information regarding the activities for the project, the project lenght = ___ weeks.
b). the total cost required for completing this project on normal time = $___
c). for reducing the duration of the project by one week, the activity that should be crashed first is activity ___
the cost of the project based on the first activity selected for crashing will increase by $___
d). the maximum weeks by which the project can be reduced by crashing =___ weeks.
total cost of crashing the project to minimum (or maximum weeks possible) = $___
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Roug The activities necessary for the completion of this project are listed in the following table: Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Roug The activities necessary for the completion of this project are listed in the following table