Question: a) Based on the given information regarding the activities for the project, the project length =______________weeks. b) The total cost required for completing this project

a) Based on the given information regarding the activities for the project, the project length =______________weeks.
b) The total cost required for completing this project on normal time = $___________
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity _________. The cost of the project based on the first activity selected for crashing will increase by $_________.
d) The maximum weeks by which the project can be reduced by crashing = _________weeks
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: a) Based on the given information regarding the activities for the project, the project length = weeksStep by Step Solution
There are 3 Steps involved in it