Question: A baseline schedule is prepared by the contractor before the start of the project, and used throughout construction to compare actual work performed _____. owner
A baseline schedule is prepared by the contractor before the start of the project, and used throughout construction to compare actual work performed _____. owner expectations against planned work and substantiate payment against delays