Question: A Bold Task in Gantt Chart View means A. It is a Task with zero duration B. It must be completed first

A Bold Task in Gantt Chart View means


 A.

It is a Task with zero duration

 

 B.

It must be completed first

 

 C.

The Task has been entered first

 

 D.

It is a Summary Task

 

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The detailed answer for the above question is provided below Ans In Gantt Chart view ... View full answer