Question: a brightspaceindwesedu 3. For this assignment, you will: a. Implement the Critical Path Method to build the schedule baseline for your Integrative Project. The schedule

a brightspaceindwesedu 3. For this assignment, you will: a. Implement the Critical Path Method to build the schedule baseline for your Integrative Project. The schedule baseline must include the following for each task: i. Duration ii. Earliest Start Time iii. Earliest Finish Time iv. Latest Start Time v. Latest Finish Time vi. Slack (also called Float) b. Additionally, as necessary, adjust the schedule baseline to ensure that all resource constraints are met. For example, if one person is needed for two different tasks at the same time, you may need to delay one of the tasks. 4. Your submission should be a a diagram showing all the listed elements for the schedule baseline