Question: A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its elosing phase. What should the risk manager of the related project have done to prevent this situation from happening? Performed the risk monitoring and closing process properly @ Created the project work plan and budget more accurately Communicated better with the organization's CEO Educated the project team on budget change requests