Question: A builder agrees in a contract to use a certain kind of construction material. However, he delays purchasing the material until absolutely necessary, hoping the
A builder agrees in a contract to use a certain kind of construction material. However, he delays purchasing the material until absolutely necessary, hoping the price will go down. When the building begins, the builder discovers that the construction material is no longer being manufactured. He then uses a lowercost brand without notifying the client. This builder has committed which of the following?
Question Select one:
A
nonfeasance
B
misfeasance
C
malfeasance
D
disfeasance
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock