Question: A builder must follow the activity chart below. Activity Letter Activity Predecessor Time (hrs) A Prepare foundation - 7 B Door frames - 2 C

A builder must follow the activity chart below.

Activity Letter Activity Predecessor Time (hrs)
A Prepare foundation - 7
B Door frames - 2
C Drains and floor base - 15
D Walls A,B 10
E Fittings D 8
F Roof D 5
G Ceiling E,F 2
H Doors & Windows E 8
I Gutters & Pipes C,G 2
J Paint outside I 3

a) From the activity chart, create a network diagram of the construction process

b) Determine the earliest completion time for all the tasks to be completed

c) Evaluate the reasonableness of the time taken to construct the dwelling.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!