Question: A building space is maintained at 76F db and 50% r.h. The peak cooling load is 10 tons with a SHR of 0.75. Ventilation

A building space is maintained at 76F db and 50% r.h. The peak cooling load is 10 tons with a SHR of 0.75. Ventilation of 1000 cfm is required of outside air at 95F db and 55% r.h. Determine the CFM, the humidity ratio of supply air and the required capacity of the cooling equipment.