Question: (a) Calculate the expected duration (te) and standard deviation (s) for each activity. (b) Draw an activity network for this project, showing only the task

(a) Calculate the expected duration (te) and

(a) Calculate the expected duration (te) and standard deviation (s) for each activity.

(b) Draw an activity network for this project, showing only the task ID in each task box.

(c) Using the expected duration calculated in Q.#01 above, calculate schedule dates(earliest & latest start and finish, and float). Indicate the critical path. (d) Given a target date of 32 days, find te, z, s, and the probability of finishing this project on time. (Refer to the graph of z values) (e) Produce a table showing the ideal number of specialists of each type needed on each day of the project. (f) What impact would there be on the project if there was only one software coder, and the rest of the information were the same as the Q.#04? (g) Create a project into Project Libre, input all information above and generate reports. Suggest values for the resource types to generate cost information report.

Activity A B C D E F CH G I Predecessor A A B B C D, F E, F G, H Optimistic Time 3d 3d 7d 3d 7d 4d 6d 7d 4d Most Likely Pessimistic Resource Time Time Type 4d 5d SA 5d 7d SD 7d 7d SD 5d 7d SC 8d 9d SC 4d 4d SC 7d 14d ST 8d 15d ST 5d 6d SA

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!