Question

1 Approved Answer

A cell uses 90 kg of a certain material each day. The material is transported in vats that hold 54 kg each. Cycle time

 

A cell uses 90 kg of a certain material each day. The material is transported in vats that hold 54 kg each. Cycle time for a kanban is about two hours. The manager has assigned a safety factor of .50. The plant operates on an eight-hour day. How many kanbans are needed?

Step by Step Solution

3.40 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

D T 2 0250 3D we have to fin... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson

12th edition

2900078024107, 78024102, 978-0078024108

More Books

Students also viewed these Mechanical Engineering questions