Question: A centre processing concert ticket applications has a four-stage process with the following loads. Assuming that the cycle time is determined by the slowest process,

A centre processing concert ticket applications

A centre processing concert ticket applications has a four-stage process with the following loads. Assuming that the cycle time is determined by the slowest process, calculate the total idle time (in minutes) and total balancing loss (as a percentage) for the operation. Load 8.74 minutes Stage 1 Stage 2 Stage 3 Stage 4 3.39 minutes 5.49 minutes 9.88 minutes Total idle time = minutes (Round to two decimal places as needed.) % (Round to two decimal places as needed.) Balancing loss =