Question: A certain manufacturing process might 5 hours in the best-case scenario, 7 hours in the most likely situation, or 10 hours under the worst possible

A certain manufacturing process might 5 hours in the best-case scenario, 7 hours in the most likely situation, or 10 hours under the worst possible circumstances. Which is approximately the most realistic duration the process might take according to PERT? A. 5 hours B. 6 hours C. 7 hours D. 8 hours