Question: A certain project has MARR = 1 5 % . Ali is the project manager and wants to select the best appropriate alternative among alternative

A certain project has MARR =15%. Ali is the project manager and wants to select the best appropriate alternative among alternative A with i**=12%, and alternative B with i**=12%. Which is the best alternative to consider?
Select one:
a. alternative B
b. do nothing alternative
c. both alternatives are accepted
d. alternative A
 A certain project has MARR =15%. Ali is the project manager