Question: A certain task is expected to take 2 4 days. The employee in charge worked diligently on the task for 2 4 days, but he

A certain task is expected to take 24 days. The employee in charge worked diligently on the
task for 24 days, but he or she accomplished only three-quarters of what is required to be done. The
entire project was planned to be completed in 120 days.
i. Calculate the task weight for this task.
ii. The actual % completion for this task.
iii. The actual relative % completion for this task