Question: A certain task is expected to take 2 4 days. The employee in charge worked diligently on the task for 2 4 days, but he
A certain task is expected to take days. The employee in charge worked diligently on the
task for days, but he or she accomplished only threequarters of what is required to be done. The
entire project was planned to be completed in days.
i Calculate the task weight for this task.
ii The actual completion for this task.
iii. The actual relative completion for this task