Question: A challenge that all project managers face when creating a WBS is to know when to stop decomposing a work package. There are seven common
A challenge that all project managers face when creating a WBS is to know when to stop decomposing a work package. There are seven common points that project managers use to stop adding levels. Two of these points are at:
a
Schedule estimation and budget estimation
b
Cost estimation and organisational planning
c
The organisational unit and scope of work
d
Risk management and deliverable estimation