Question: A change has been approved by the change control board. As the team begins implementing the change, it becomes immediately obvious that adfitional equipment will

A change has been approved by the change control board. As the team begins implementing the change, it becomes immediately obvious that adfitional equipment will be needed, which will increase the cost of the project by about 15%, a fact previously not identified. This is an example of:
A.) A poor change control process
B.) Secondary change
C.) Residual risk
D.) Secondary risk