Question: A change order is a written amendment to the contract signed by the Owner and the Contractor stating their agreement upon a number of things.
A change order is a written amendment to the contract signed by the Owner and the Contractor stating their agreement upon a number of things. Which one of the following will not be part of their potential agreement for executing a change order?
| a. A scope of change in the work | ||
| b. The method of price adjustment | ||
| c. The method of holdback releases | ||
| d. The amount of the adjustment in the contract price | ||
| e. The extent of the adjustment in the contract time |