Question: A change request submitted by the project sponsor has an effect on several other projects within the organization. If the change request appears to be

A change request submitted by the project sponsor has an effect on several other projects within the organization. If the change request appears to be a positive addition to the project, who should you ask to approve the change request?
the project customer
the change review board
the organization's executive board
The project sponsor requested the change, so you don't have to ask anyone to approve it.