Question: A choice must be made between two projects, A and B. The following information is provided on each project: Year Project A Project B (i)

A choice must be made between two projects, A and B. The following information is provided on each project:

Year

Project A

Project B

(i) Initial investment

(ii) Annual net cash inflows:

1

2

3

4

5

R22 000

R10 000

R8 000

R6 000

R4 000

R3 000

R22 000

R3 000

R4 000

R6 000

R8 000

R10 000

R31 000

R31 000

(iii) The current cost of capital is 15%

Future-value Factors

Period (n)

5%

10%

15%

1

1.0500

1.1000

1.1500

2

1.1025

1.2100

1.3225

3

1.1576

1.3310

1.5209

4

1.2155

1.4641

1.7490

5

1.2763

1.6105

2.0114

Discounting Factors

Period (n)

5%

10%

15%

1

0.9524

0.9091

0.8696

2

0.9070

0.8264

0.7561

3

0.8638

0.7513

0.6575

4

0.8227

0.6830

0.5718

5

0.7835

0.6209

0.4972

The Net present value for Project B is?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!